Change Order Template: What Contractors Should Include

byAlex Solo9 min read

Wondering what to put in a change order template so you actually get paid for extra work? The reassuring answer is that it doesn't have to be complicated, but it does need to be clear.

On construction and project work, scope changes are normal. A client asks for a different finish, hidden site conditions appear, a supplier delay affects the schedule, or the project owner wants extra work added halfway through.

The problem usually isn't the change itself. It's the gap between what one person thought was approved and what the other person thought was included. A good change order form helps close that gap before the work, cost, or deadline becomes a dispute.

What Is A Change Order?

A change order is a written agreement that changes the original contract scope, statement of work, price, schedule, or another key project term.

For private construction projects in the US, there's no single federal change order law that applies to every job. Your contract is usually the starting point, with state construction law, licensing rules, lien rules, prompt payment rules, and public project requirements potentially changing the answer.

If the project is a federal government contract, different rules may apply, including rules under the Federal Acquisition Regulation. Most small business projects, though, are governed mainly by the written contract and general contract principles.

A change order can deal with things like:

  • Extra labor or materials
  • A revised drawing, specification, or design
  • A substituted product or finish
  • A delay caused by weather, access issues, inspections, or owner decisions
  • Unexpected site conditions
  • A credit for work removed from the scope
  • A new completion date or milestone date

Think of it as a small contract amendment to the main contract. It doesn't replace your original agreement. It records the change and says how that change affects the job.

A template can be a useful starting point, but it shouldn't be treated as a finished legal document. The right wording depends on your contract, your role, the project type, and the state law that applies.

When Do You Need A Change Order Form?

You need a change order form whenever the project is changing in a way that affects scope, price, timing, risk, or responsibility.

If the change is minor and has no cost or deadline impact, an email confirmation may be enough under your contract. But if you need to buy materials, put extra workers on the job, extend your schedule, or rely on the owner's approval, get it in writing before you proceed.

Common triggers include:

  • The owner asks for additional work that wasn't in the original scope
  • The plans or specifications are revised
  • The owner supplies late information, approvals, or access
  • A subcontractor discovers concealed conditions
  • Materials become unavailable and a substitute is needed
  • A permit, inspection, or utility issue delays the work
  • The owner asks you to accelerate the job
  • You agree to remove work and give a credit

For example, say Maria runs a small remodeling company. Her original contract is $48,000 to renovate a retail fit-out. Halfway through, the owner asks for a feature wall and upgraded lighting that aren't in the scope.

Maria prices the extra framing and electrical materials at $3,200, extra labor at $2,400, overhead and profit at 15% which is $840, and an additional permit fee of $250. Her change order totals $6,690 and extends the completion date by 4 business days.

If Maria starts the work based on a friendly conversation, she may struggle later if the owner says the feature wall was included. If she uses a signed change order first, everyone can see the cost, time impact, and approval.

What Should A Change Order Template Include?

A change order template should include enough detail for someone outside the project to understand exactly what changed, why it changed, what it costs, and how it affects the schedule.

Here is a practical fill-in outline you can use as a drafting checklist. Have a lawyer tailor it before you use it on a live project, especially if you're relying on it across multiple jobs.

  1. Project Details: Write the project name, site address, contract date, owner, contractor, and any architect, designer, or project manager details.
  2. Change Order Number: Use a clear numbering system, such as CO-001, so each change can be tracked.
  3. Description Of The Change: Describe the added, removed, or changed work in plain English, with references to drawings, plans, specifications, or emails where helpful.
  4. Reason For The Change: State whether the change is owner-requested, caused by site conditions, required by an authority, caused by delay, or agreed for another reason.
  5. Price Adjustment: Show the cost increase or decrease, including labor, materials, equipment, subcontractors, markup, taxes, shipping, permits, and credits.
  6. Payment Terms: Say when the change order amount is payable, such as on approval, with the next progress invoice, or under a specific milestone.
  7. Schedule Impact: State whether the completion date changes and, if so, by how many calendar days or business days.
  8. No Other Changes: Confirm that the original contract stays in place except for the changes listed in the form.
  9. Approval And Signatures: Include signature blocks for the people with authority to approve the change, plus the date of approval.
  10. Attachments: List any updated drawings, quotes, photos, product specifications, or site instructions attached to the form.

Try to avoid vague phrases like "as discussed" or "extra work to be done." Those words feel easy in the moment, but they don't help much if an invoice is challenged later.

How Do You Write A Change Order Step By Step?

You write a change order by starting with the contract, then clearly recording the change, the price, the timing, and the approval before the work starts.

Here's a simple process you can follow on most projects.

Step 1: Check The Original Contract

Start by reading the change order clause in your contract. It may say who can approve changes, how notices must be sent, whether oral approvals count, and when claims for extra time or money must be submitted.

Some contracts have strict notice requirements. If you miss them, you may lose the right to claim payment or an extension, even if the extra work was real.

Step 2: Define The Exact Scope Change

Describe the change as if the person reading it wasn't at the site meeting. Include quantities, locations, materials, drawings, product names, finishes, and exclusions.

For example, "Install 18 linear feet of additional upper cabinetry along the west wall using the same finish as drawing A4.2" is much stronger than "add more cabinets."

Step 3: Price It Clearly

Break the price down enough to make it credible. You don't always need every receipt attached, but you should show the main drivers of the cost.

A clear price section might include:

  • Labor hours and labor rate
  • Material quantities and unit costs
  • Subcontractor quotes
  • Equipment or rental costs
  • Permit, inspection, delivery, or disposal fees
  • Overhead and profit markup, if allowed by the contract
  • Sales or use tax treatment, if applicable to the transaction

Tax treatment can vary by state and project type, so check with your tax adviser if you're unsure.

Step 4: Record The Time Impact

If the change affects the schedule, say so directly. State whether you need 2 days, 10 days, or no extension at all.

Be clear whether you're using calendar days or business days. If weather, inspections, or owner-supplied items may add more delay, note that the change order only covers the known delay unless the contract says something different.

Step 5: Get The Right Signature

A change order is only useful if the person signing has authority to approve it. A site conversation with someone who can't approve budget changes may not protect you.

If you're dealing with an owner representative, project manager, architect, or tenant, check the contract to see who can bind the project owner.

What Should Your Change Order Contract Clause Say?

Your change order contract clause should say how changes are requested, priced, approved, and treated if urgent work has to happen before signatures are complete.

This clause matters because the template and the contract need to work together. If your contract says changes must be signed by both parties, but your team often relies on texts from a site manager, you may be creating avoidable risk.

A practical change order contract clause usually covers:

  • Written approval: Whether changes must be approved in writing before work starts.
  • Authorized people: Who can request and approve a change on behalf of each party.
  • Pricing method: Whether changes are fixed price, time and materials, unit rate, or another agreed method.
  • Markup: Whether overhead, profit, supervision, and administrative costs can be added.
  • Schedule extensions: How the completion date is adjusted if the change causes delay.
  • Emergency or field changes: What happens if urgent work is needed to protect people, property, or the project.
  • Disputed changes: Whether work continues while the parties resolve a price or time disagreement.
  • Recordkeeping: What daily reports, timesheets, photos, invoices, or receipts must be kept.

The Uniform Commercial Code can affect contracts for goods, including some supplier agreements, but construction contracts are often treated mainly as service or mixed contracts under state law. That's one reason a clause that works well for product supply may not work properly for construction or installation work.

If you've pulled a construction change order template from the internet, compare it against your actual contract as part of a contract review. A neat form won't help much if it conflicts with the rules you already agreed to.

Frequently Asked Questions

Can A Change Order Be Approved By Email?

Yes, a change order can often be approved by email if your contract allows written electronic approval and the person approving it has authority. Some contracts require a signed form, so check the wording before you rely on an email alone.

Can You Charge For Extra Work Without A Signed Change Order?

Sometimes, but it's harder. You may have arguments under the contract or general contract principles if the owner requested and accepted the work, but without written approval you may face a payment dispute.

What If The Work Has Already Been Done?

Put the change in writing as soon as you can. Send a summary of the work, why it was needed, dates performed, labor and material records, photos, and the amount claimed, then ask for written approval or payment.

Do Change Orders Affect Lien Rights?

They can. Lien rights, notice deadlines, lien waiver wording, and payment claim rules depend heavily on state law and the project type, so get advice early if an unpaid change order could become a lien issue.

Key Takeaways

  • A change order is a written update to your original contract for changed scope, price, schedule, or responsibility.
  • Your change order form should clearly describe the work, reason for the change, price, payment timing, schedule impact, and approval.
  • Your contract clause and template need to match, especially on who can approve changes and whether approval must happen before work starts.
  • Clear pricing and schedule details help you avoid arguments over whether extra work was included in the original scope.
  • If work has already been done, collect records quickly and confirm the change in writing as soon as possible.

If you'd like help with reviewing your change order form, tailoring your change order clause, or documenting project variations before they turn into payment disputes, you can reach our team at (888) 449-8437 or team@sprintlaw.com. Where legal services are required, they're provided by licensed US lawyers at ElevateNext US, LLC, a trusted US law firm, through the Sprintlaw platform.

Drafted by Taylor, Sprintlaw's AI, and overseen by Alex Solo. How we write

Alex Solo
Alex SoloCo-Founder

Alex is Sprintlaw's co-founder and a legal technology leader. He holds law and media degrees from the University of Sydney and has been recognized by Australasian Lawyer, Lawyers Weekly and the Sydney Young Entrepreneur Awards for his work building Sprintlaw and improving access to business legal support.

Need legal help?

Get in touch with our team

Tell us what you need and we'll come back with a fixed-fee quote - no obligation, no surprises.

Keep reading

Related Articles

Change Order Template: What To Include

Change Order Template: What To Include

Scope creep does not have to derail your project. A clear change order helps you agree on extra work, fees and timelines before your team proceeds.

Nov 17, 2026
Read more
Change Order Clauses For US Service Contracts

Change Order Clauses For US Service Contracts

Extra work can quietly eat your profit. A well drafted change order clause helps you pause, price and approve changes before your team starts the additional work.

Oct 25, 2026
Read more
Change Order Review: Payment, Liability And Termination Terms To Check

Change Order Review: Payment, Liability And Termination Terms To Check

Change orders can significantly impact your construction project's cost, timeline, and risk. This guide explains what US businesses should review in a change order template, including payment, liability, and state-law considerations.

Jun 25, 2026
Read more
Change Order Review: Practical Drafting Points For Growing Businesses

Change Order Review: Practical Drafting Points For Growing Businesses

Change orders are critical in construction projects. This guide explains what US businesses should review in a change order template, including scope, payment, liability, and state-law issues, with practical examples and checklists.

Sep 10, 2026
Read more
Change Order Template Review Checklist For US Startups And Small Businesses

Change Order Template Review Checklist For US Startups And Small Businesses

A thorough checklist for reviewing change order templates in US construction and service contracts. Learn what to look for, avoid common legal mistakes, and understand how state rules can impact your change order process.

Jun 25, 2026
Read more
Landscape Contract Template: What To Include

Landscape Contract Template: What To Include

A clear landscaping contract helps you lock in scope, payment terms, change orders, weather delays and customer approvals before your crew starts work.

Nov 14, 2026
Read more
Need support?

Need help with your business legals?

Speak with Sprintlaw to get practical legal support and fixed-fee options tailored to your business.